The Nigerian National Petroleum Company Limited and the contractor parties of Oil Mining Licence 118 have signed agreements aimed at advancing the Bonga Southwest/Aparo deepwater project towards a Final Investment Decision.
The agreements were executed on Monday by NNPC and the OML 118 contractor parties, comprising Shell Nigeria Exploration and Production Company Limited, Esso Exploration and Production Nigeria (Deepwater) Limited and Nigerian Agip Exploration Limited.
According to NNPC spokesperson Andy Adeh, the agreements include an addendum to the OML 118 Production Sharing Contract and an addendum to the Dispute Settlement Agreement.
NNPC said the development followed the approval of the Deep Offshore Oil and Gas Projects Incentives (Tax Remission) Order, 2026, by President Bola Tinubu.
The company said the agreements give effect to the fiscal and commercial terms approved by the Federal Government to support the development of Bonga Southwest/Aparo.
NNPC said the project is expected to attract between $15bn and $21bn in investment over its lifespan, while reaching peak production of approximately 175,000 barrels of oil per day and 140 million standard cubic feet of gas per day.
The project is expected to contribute to Nigeria’s economy through increased oil and gas production, government revenue, foreign exchange earnings, local content development and employment opportunities.
Pre-FEED phase completed
The contractor parties also announced the successful completion of the project’s pre-Front End Engineering Design phase.
NNPC said the milestone would help mature the technical and commercial scope of the project ahead of the FEED phase, subject to the required partner, assurance and governance processes.
The company disclosed that a bidder had been identified as the preferred Floating Production Storage and Offloading contractor following a competitive selection process.
The selection, however, remains subject to the completion of applicable partner, regulatory, assurance and governance procedures.
NNPC said the preferred contractor selection would provide a basis for progressing the FPSO concept into FEED and carrying out further engineering and commercial work towards the Final Investment Decision.
It stressed that any eventual award of the FPSO Engineering, Procurement, Construction and Installation contract would remain subject to the completion of all required approvals.
Project expected to boost oil output
When operational, NNPC said Bonga Southwest/Aparo could become one of Nigeria’s major new deepwater production hubs.
The project is expected to support the country’s efforts to increase oil and gas production while generating opportunities for Nigerian contractors and suppliers.
It is also projected to create direct and indirect jobs in areas including engineering, fabrication, offshore construction, logistics and operations.
Speaking on the development, NNPC Group Chief Executive Officer, Bayo Ojulari, said the execution of the agreements demonstrated the impact of the Federal Government’s reforms on attracting investment into the energy sector.
“This is about unlocking a major deepwater project and demonstrating that Nigeria has a competitive fiscal framework and a clear pathway for sustainable investment in its energy sector,” Ojulari said.
He added that NNPC would continue working with the Federal Government, project partners and other stakeholders to ensure that the development delivers maximum value to Nigeria and its citizens.